Hinton Haunted House ---------------- Behind the Scenes - 2002
![]() Here's where it all starts.
This was a side-by-side tennis court.
In this photo you see wall panels going up near the main entrance.
Soon the outer fabric wall will be stretched and attached, and the
serious work can begin on the inside.
October 12, 2002
![]() A ten foot roll of weed barrier / ground cover fabric
is stretched around the perimeter of the old tennis court.
![]() Wall panels made of 2 X 4 lumber are covered with the
same ground cover cloth. When stretched and stapled, this
fabric is amazingly tough. Some of these 8' X 8' panels have been
in use for three seasons already.
All of the hallways and rooms are made with these panels.
![]() This is the view from above the exit of the 2002 haunt.
The basic construction is nearly complete.
October 19, 2002
The last weekend before the haunting begins ...
![]() What kind of haunt would it be without a table full of skeletons?
The most obvious change is the facade.
![]() ![]() ![]() With a few man-hours, a few tools, a few bolts,
and a professional backhoe operator, the facade went up smoothly.
Everyone is hard at work finishing the rooms within the haunt.
![]() Main Hallway Bridge (Tunnel) The Laboratory
![]() Pop -Up Scene Flying Crank Ghost Dungeon Scene
![]() Chainsaw Runner's Room Graveyard entrance Multiple Doorways - Exit
---- A few assorted photos ----
![]() The Graveyard Crew The Door Man
Pop Up Ghoul A Chainsaw Runner Webbing The Dungeon
![]() Mummy Toxic Waste ...So Much To Do....
For the hardcore back stage haunt enthusiast,
|
||